|
Reduce mine operating costs by 20 – 30%
With out capital expenditure
Our associates, have
had considerable success recently in mine optimisation.
Staff comprise very experienced mine managers, and
professionally qualified mining engineers, mine planners and
equipment maintenance experts. Staff are not the general,
non-mining qualified, “management consultants” seen at times in
the industry.
Without impinging on client confidentiality, specific gains and
dramatic cost reductions by our associates have achieved over
the last 5 years for clients are detailed below.
Hunter Valley Coal Mine, New South Wales, Australia:
Produced a radically new Five Year Business Plan giving rise to
the following achievements, an innovative new Five Year Mine
Plan with significant changes to mining methodology, a Major
Fleet reduction: from 71 to 44; and annual operating costs
reduced by $ 30M. Annual sales tonnes were about 4.5 Mtpa.
Venezuelan Coal Mine, Zulia Province, Venezuela: Major
increase in annual coal production from 3.9 Mt/annum to 5.1
Mt/annum in 1998 and produced at 6.5 Mt/annum for the first
quarter of 1999. Formulated a new five year mining plan better
suited to the deposit; annual operating costs reduced by $ 20M
US; shut down10 major items of plant, while managing the
operation over a period of fifteen months.
Bowen Basin Coal Mine, Queensland, Australia: Formulated
Five Year Budget with annual cash cost reduction of 20% ($20
Million); implemented key points of plan while managing the
operation over a period of twelve months. Achieved savings of
$5Mpa in the coal handling and preparation plant area by
instituting rigorous maintenance budget and control procedures,
installed new water management system in the mine, identified
major design impediments to the operations and was part way
through a process of resolving these during the management
period.
Second Bowen Basin Coal Mine, Queensland, Australia:
Conducted a benchmark five year plan including a detailed
maintenance budget of all the mobile equipment on site. This
highlighted a number of areas to be improved, such as the
management of maintenance processes, efficiency of labour, and
optimization of equipment within the operation. Savings of
$15Mpa were highlighted, much of which was picked up over the
next two years.
Our associates approach is very much “hands on” and
focuses on the key design and operational issues impacting on
productivity, coal recovery and cost. Sites are reviewed on a
global perspective, looking at how all the elements interact.
The initial step is a 3 week review of site operations to
identify and report on the key areas of improvement, $ value
opportunity, and the steps necessary to reach these goals. The
client can then decide what aspects they wish to correct. Our
associates can remain on site if necessary to ensure that the
plan is implemented and results achieved.

Coal Wash Plant case study shows increase in mine
profits
by US$ 3 million per annum and increase in pit recovery and
mineable reserves by 5 – 7%.
The general logic for having a wash plant in a moderately high
strip ratio mine is normally well justified, and is standard
operating practice in many coal mines around the world. After
spending so much money on overburden removal it is critical to
recover as much coal as possible.
A recent case study was considered for a typical major
Indonesian coal mine.
E.g. For a mine with a strip ratio of say 5.0 Bcm/tonne, and
costs to remove overburden at approximately US$ 1.25/Bcm, there
fore total costs for removal of overburden per tonne of coal is
US$ 6.25 /tonne.
Current assumptions are for the washplant to recover ‘dirty
coal’ (coal contaminated or mixed with overburden) to increase
total pit coal recovery by about 5% up to 7%. Thereby increase
total pit recovery from currently 90% upto 95 – 97%. Initial
capital investment of some $2.5 million for a wash plant of 1
million tonnes per annum capacity.
|
|
Cost saving on overburden
per coal tonne
|
$6.25/tonne
|
|
Minus wash plant costs
(Assume by contractor)
|
$1.50/tonne
|
|
Nett saving
|
$4.75/tonne
|
|
Average 6% extra coal
recovery For a 10 million tonner per annum mine
|
600 000 tonne/yr
|
|
Extra profit
|
$ 2.85 million p.a.
|
|
Payback time for the wash
plant
|
less than 1 year
|
|
The wash plant could also simply be a contractor operation, thus
avoiding any capital expenditure for the mine.
A wash plant can also effectively increases a mine’s recoverable
reserves, and extend mine life, by 5% - 7% which is also a major
benefit.
Our associates have over 30 years of experience in the study and
evalution as to whether a mine needs a wash plant, and in the
design and costing of such an operation. We also work with
contractors who have specific experience in the operation of
wash plants on a $ per tonne contract basis for the customer.

US$ 24 million per annum increase in mine profits, and
30% reduction in costs, by
Early “In-Pit” dumping of overburden
waste – a case study
Detailed mine planning and scheduleing can allow a mine to more
rapidly achieve a situation where the pit mine can reach final
pit depth/limits earlier, and a allow for in pit back filling of
waste. This action can massively reduce truck haul distances and
therefore costs, for overburden. Also it can reduce amount of
area disturbed ex-pit, and lower over all rehabilitation
expenses.
E.g. Detailed mine planning and scheduling expertise was applied
to one recent case study of a major coal mine where current haul
distances on average were 1.8km one way to ex-pit waste dumps.
This study showed that when in-pit waste dumping could be
introduced, truck haul distances could be reduced from 1.8km
down to about 0.9km, and save some $0.40 / Bcm. This could
reduce the current overburden rate from $1.25 down to $0.85/Bcm
(30% reduction). For a mine with a nominal strip ratio of 6.0
Bcm/tonne, producing 10 million tonnes coal per annum, this
reflects in significant extra profit.
Extra profit 6.0 bcm/t x 10 mtpa x $0.40 = $ 24 million per
year.
Our associates have conducted detailed
mine planning studies on numerous coal mines through out the
world, and have the expertise to balance to the factors involved
in scheduling a complex multi seam, variable quallity, coal
mine, to bring about the most effective means of in pit back
filling.

40% costs reduction by alternative surface
mining methods -
Direct Dozer Push applications
In the face of significantly
decreased coal prices and stiff international competition from
Australia and China etc. Indonesia need’s to lift it self up a
“quantum step” in becoming more cost competitive, employing mining
methods and technology that are to international mining standards and
“best practices.”
For certain mine site pit and seam
geometries, the application of direct dozer methods can
bring about massive cost reductions.
These methods are standard practice world wide, and
there increased application in to the Asian and Indonesian coal
industry will become more necessary in order to reduce costs and
maintain competitive position.
As an example, typical hydraulic excavator
and truck operations in Kalimantan, cost approximately US$ 1.20/Bcm.
A direct dozer push operation can reduce costs to some US$ 0.70 /Bcm (40%
reduction).
There are some excellent seam conditions in
Kalimantan very amenable to direct dozer push methods.
Experienced contractors can carry out such operations on a unit basis
$ / Bcm.
Our associates have extensive experience in
evaluating dozer push applications and also can propose
an experienced contractors.

Upgrading to larger size mobile mining equipment
gives cost savings of 20 – 30%
In the Indonesian coal fields further studies show that when upgrading
fleet size from say the current typical standard of excavator and
truck fleet from now predominantly a fleet of 13m3 excavators and 85
tonne trucks to double the size with 25m3 excavators and 160 tonne
trucks. As a rule of thumb, if the fleet size can be doubled then
costs can be reduced by some 30%. For at least overburden operations
this should be very feasible, and an obvious step to bring an
operation up to world class standards. For a typical large size mine
savings could be approximately;
6 bcm/tonne x 10 mtpa x ($1.25/bcm x 30%) = $ 22 million per annum
This could be a contractor operation, with the normal term of the
contract being extended from say the current practice of a 3 year term
out to say 5 to 10 years to justify the capital investment by the
contractor.
Our Associates have extensive experience in the mine planning required
to implement such fleet upgrades, plus can implement such larger size
equipment as a contractor.

30%
to 50% mine cost reductions by replacing long truck hauls with
In Pit Crushing and Overland Conveying Systems
In the face
of significantly decreased coal prices and stiff international
competition from Australia and China etc. Indonesia must lift it self
up a “quantum step” in becoming more cost competitive, employing
mining methods and technology that are to international mining
standards and “best practices.”
Various systems can be further studied to replace long truck hauls
with conveyors. This is a capital intensive approach, but generally
gives massive operating cost savings and rapid pay back times, if
volumes are large. For example case studies have been conducted at
several large size Indonesian mines, which show 30% to 50% cost
savings for overburden and coal transportation. Systems are capital
intensive, with typical a In-Pit crushing and conveying system costing
in the range of US$ 30 – 40 million, how ever payback time is rapid,
normally with in 2 years.
A significant extra benefit of these systems, is if mine costs can be
significantly reduced by several dollars per tonne, then open cut pits
can be extended to greater depths, and more reserves recovered, there
by increasing mine life considerably.
These type systems can also be introduced by contractors on a unit
rate price basis, thus avoiding the mine owner spending capital. For
example similar to mining contractors working at the Mae Moh mine in
Thailand, using this type of conveying systems on the basis of a 10
year contract.
Our Associates, hold the
majority of market share in the world for large scale In Pit Crushing
and Conveyor systems. Our associates are experts in evaluating mine planning
needs, and equipment supply. Our associates have over
40 years of experience in Indonesia, supplying major size coal handling
equipment to Indonesian coal mines.
In
pit crushing and conveying systems for either overburden and coal
(international reference).
Overland
coal conveyor. Long distance continuous conveyor comprising both
vertical and horizontal curves (international reference).

Due
diligence studies required for coal mines in order to satisfy banks
and qualify for project financing
Our
Associates, are a major international mining
consulting company. They have acted on behalf of major banks, and
financial institutions, for many of Indonesia’s and S.E. Asia’s IPP
projects, conducting due diligence on many coal mines. They have a
thorough understanding of bank’s requirements from mines in order to
satisfy project financing criteria.

|